Report of 64th meeting of the CFHT SAC
Waimea, Hawaii, 13-15 November 2003
The
meeting was attended by SAC members P. Bastien, J.-L. Beuzit, D. Bohlender
(chair), E. Emsellem, C. Ftaclas, G. Mitchell, P. Petitjean (vice-chair),
C. Pritchet, and G. Soucail. B. Tully was unable to attend. KAO representative
H. Kim and Taiwan representative S.-Y. Wang were present as observers.
C. Veillet, D. Salmon, J.-C. Cuillandre, O. Lai, T. Forveille, E. Magnier,
G. Barrick, W. Rambold, P. Puget, P. Martin, and N. Manset participated
in presentations and discussions.
64th SAC Meeting Agenda:
14-15 November 2003
-
Technical activities report (Salmon)
-
DEC oscillations
-
GRIF
-
Instrument and Project reports
-
MegaPrime (Rambold/Cuillandre)
-
WIRCAM (Puget/Forveille)
-
Espadons (Barrick/Manset)
i.Project
status and schedule
ii.Commissioning
-
Pueo Nui (Salmon/Lai/Cuillandre)
i.Project
team, plan, and schedule
ii.Flyeyes
-
Ohana Update (Lai)
-
CFHT environmental data
(Magnier/Veillet)
i.Second
skyprobe
ii.DIMM
iii.Mauna
Kea weather services
-
CFHTLS
-
CFHTLS report (Mellier)
-
DOG report (Cuillandre)
-
External review (SAC)
-
WIRCAM SG (Beuzit)
-
Filters
-
Surveys
-
Telescope use and scheduling (Veillet)
-
2004A schedule
-
Trends in instrument use
-
Duplicate observations issue
-
2004 User's Meeting (SAC/CFHT)
-
15-17 May 2004, Victoria, BC
-
Preliminary program discussions
-
CFHT Future (Veillet)
-
Other items
-
CFH12K disposition
-
Staff; Astronomy Group
-
SAC membership; Chairmanship
-
TAC membership
-
Next meeting
1. Technical
Activities Report
D.
Salmon presented the CFHT technical activities report. No changes
have been made to the current project priorities. It was noted that
the MegaPrime and WIRCAM projects alone will consume about 80% of CFHT's
available manpower for the next year.
SAC
was pleased to learn that with the removal of the last summit HP1000 computers
a completely autonomous TCSIV system has finally been realized.
Significant
progress has been made on reducing the impact of the DEC oscillations on
observers, but a complete solution has not yet been found and may require
substantial changes in telescope hardware.CFHT
will continue to work on this issue and update SAC at the next meeting.SAC
congratulates CFHT staff on the progress that as been made and continues
to view a full solution of this long-term problem as a high priority as
reflected in the current CFHT project priority list.
The defective GRIF filter plane wheel has been sent
to Paris for examination by Observatoire de Paris staff and will be returned
to CFHT in time for the late 2003B observing runs (which will NOT require
full operation of the wheel).It
will be returned to OdP immediately after the 2003B runs for final repairs,
and as a result will not be available for users in 2004A.CFHT
will provide a report at the next SAC meeting.
2. Instrument
and Project Reports
· MegaPrime
W. Rambold presented a report on the technical activities
carried out by CFHT staff for the MegaPrime project. For the most part
the camera is performing quite reliably.The
wide field corrector (WFC) is currently believed to be at its best mechanical
adjustment.Overall image quality
concerns remain and L1 of the WFC is the prime suspect.CFHT
will attempt to re-characterize the lens at its normal operating temperature.
In response to a previous SAC recommendation, spare
control electronics are now available.
Intermittent failures of CCD#3 will be addressed
early in 2004 with help from CEA.
The MegaPrime filter handling mechanism has experienced
some technical problems because of the 30-40 filter changes normally made
each night.CFHT staff have identified
weak links in the design and are currently researching long-term solutions.
Autofocus of the camera is still under development
but has made considerable progress and it is hoped that this automation
will be concluded in a few months.In
any case overheads for guide star acquisition and focusing have been greatly
reduced to just a few 10's of seconds on all areas of the sky.
Based on this report SAC makes the following recommendations:
SAC Recommendation #1:
SAC recommends that CFHT proceed as quickly
as possible with measurements of L1 of the MegaPrime wide field corrector
as a first step in determining the reason for the camera's image quality
not meeting specifications.
SAC recommends that CFHT continue efforts
to correct the intermittent failure of MegaPrime's CCD #3, complete implementation
of autofocus capabilities, and improve the reliability of the camera's
filter handling mechanism.
J.-C. Cuillandre presented a report on the MegaPrime
and Elixir scientific activities conducted by CFHT staff.Of
particular note is the release of greatly improved MegaPrime web pages
with extremely detailed information on all aspects of observing with the
camera.
· WIRCAM
P. Puget presented a report on progress of the WIRCAM
project.Uncertainty remains in the
delivery of the detector arrays.Originally
expected in early 2004, Rockwell now hopes to deliver all detectors by
2004 April.The ASICS have had warm
tests of their functionality; final tests of the packaged prototypes under
operating temperatures are expected early in 2004.The
report noted that an interim SDSU3 controller might almost reach readout
performance goals - 2 seconds for double correlated sampling readout versus
the specification of 1.5 seconds.
The delay in the detector delivery has resulted
in a 4 to 5 month delay in the project when compared to the previous schedule.
The overall project plan currently has on-sky tests scheduled for the autumn
of 2004.WIRCAM should be available
to observers in 2005A, which means that a call for WIRCAM proposals (see
SG group section below) should be made no later than the summer of 2004.
· Espadons
G. Barrick presented a technical report for the
Espadons spectrograph while N. Manset presented a report on the Espadons
team's commissioning plans and demonstration science programs.The
latter will involve two programs: a search for weak magnetic fields in
hot stars including OB, Be and Herbig Ae stars, and Zeeman Doppler imaging
of a fully convective M dwarf star.
If the current schedule is maintained Espadons should
see first light in early May 2004 and commissioning will take place until
the end of 2004A with demonstration science currently scheduled in late
July 2004.Given concerns in the
possibility of maintaining this schedule and CFHT staff commitment to the
MegaPrime and WIRCAM projects, SAC would prefer that a call for Espadons
proposals not be made until it is certain that the instrument is fully
operational.As a result, SAC recommends:
SAC Recommendation #3:
If the current schedule for Espadons is
maintained through 2004 February, SAC recommends that Espadons be made
officially available to the user community in a call for proposals in semester
2005A.This recommendation will
be revisited at the 2004 May SAC meeting.At
the discretion of the CFHT Executive Director, for the 2004B Call for Proposals
CFHT can consider offering Espadons as a possible alternative to Gecko
for successful Gecko proposals.
· Pueo
Nui
D. Salmon and O. Lai presented a report on Pueo
Nui. Pueo Nui, which includes the Fly-Eyes upgrade, assumed the status
of a true CFHT project in the fall of 2003. Staff commitments to
other projects such as MegaPrime have prevented completion of the detailed
Pueo Nui study requested at the last SAC meeting, but first efforts in
this regard have indicated that the Pueo Nui Workshop's recommended scientific
goal of a Strehl ratio of 0.90 in the K band is very ambitious, and possibly
not feasible with the relatively simple and fast upgrade of the current
AOB system first envisioned.
O. Lai also presented a summary of an alternative
two-stage AO system.
SAC discussed Pueo Nui at length. There continue
to be compelling scientific and technological arguments for pursuing advanced
AO systems at CFHT. Pueo Nui's uniqueness continues to be the
capability of high-strehl imaging, extended to optical wavelengths.
While the Workshop clearly indicated that scientific targets for the CFHT
would be limited, such technology will be of obvious interest to other
large telescope projects. SAC therefore makes the following recommendation:
SAC Recommendation #4:
As there continue to be compelling scientific
and technological arguments for pursuing the study and development of an
advanced AO system at CFHT, SAC recommends that CFHT complete the feasibility
study of the originally proposed Pueo Nui project, which consists of an
upgrade of the deformable mirror and real-time computer, and the implementation
of the Fly-Eyes detector. The main goal of this study is to determine
the realistic delivered Strehl ratio of such an upgraded CFHT AO system,
and compare these with the scientific goals discussed at the Pueo Nui workshop.
SAC would like to review this study at the 2004 November SAC meeting at
the latest.
SAC recognizes that there are additional very interesting
ideas from CFHT staff regarding the extension, on longer timescales, of
the diffraction limited optical and near-IR imaging capabilities of CFHT,
possibly over the entire sky observable from Mauna Kea. SAC feels
that it is very important to maintain CFHT staff involvement in such state-of-the-art
instrumentation research and development and therefore encourages CFHT
to continue to investigate these other AO concepts, such as the two-stage
system presented at the current meeting. The SAC would obviously
be willing to review any proposal seeking to address these more ambitious
goals at a future meeting.
· O'hana
O. Lai presented a brief summary of recent O'hana
activities.Phase I work is almost
complete with injection tests completed on CFHT, Keck, and Gemini.Phase
II work is now progressing quite well.The
O'hana beam combiner was successfully tested at IOTA in 2003 June and the
CFHT-Gemini delay line is being assembled and tested in Meudon.Fluoride
and silicate glass fibers have been manufactured.
Upon successful completion of Phase II work SAC
will be required to evaluate plans for Phase III.
· CFHT
Environmental Data
E. Magnier presented a summary of recent work on
the Differential Image Motion Monitor (DIMM).First
tests with the new, customized 14" Meade telescope were carried out on
7 November.Work must still be done
to solve remaining problems with control of the Meade's TCS, but much of
the functionality required has been successfully demonstrated, including
communication between the Meade and CFHT TCS's, conversion of the dome
slit coordinates to RA and DEC, slewing the Meade to the selected monitor
star, etc.O. Lai will assume responsibility
for the DIMM project after the departure of E. Magnier.
E. Magnier also presented
a summary of his study of the long-term stability of the absolute photometry
from the CFH12K camera.Of note is
an interesting long-term (approximately 1 year) variability of a few percent
in the zero point that is not clearly related to the primary mirror
condition, or other known factors.
3. CFHTLS
G. Soucail, representing the CFHTLS Steering Group,
presented SAC with reports of SG group activities as well as reports for
the Deep, Wide, and Very Wide survey components of the CFHTLS.C.
Pritchet provided a summary of the CFHTLS SNe programs.
Deep Survey
The location of the D2 field has been moved to the
COSMOS/ACS survey area at RA ~10 hr.The
proposal to move the field was circulated to the CFHTLS email distribution
list for discussion, but few comments were made by the member communities.The
D2 field is now outside the W2 field.A
few SAC members noted that they did not receive the above email.This
caused some concern about the completeness of the CFHTLS mailing lists
maintained by CFHT, but may very well be an unintended result of some user's
SPAM filters.
A frequently updated web page for the CFHTLS Deep
Survey can be found at http://webast.ast.obs-mip.fr/projects/CFHTLS_deep.
SN Survey
A web site providing information about the CFHTLS
supernovae programs can be found at
http://www.cfht.hawaii.edu/SNLS.
Of
particular note for the SNe program is the fact that a formal collaboration
between Canadian and French groups has been established, complete with
an MOU.
Pain is currently the chair
of the consortium.
Each team currently runs its SNe detection pipeline
independently.For SN candidates
brighter than i'=24 detections by the two pipelines agree very well, and
are quite reliable to i'=24.5.80%
of all variables at the latter level are real variables, but are not necessarily
SNe.It is thought that eventually
one pipeline will be shut down to enable a greater concentration on the
spectroscopic follow-up.
Follow-up spectroscopic observations are proceeding
very well and the survey team believes that the goals of the survey are
indeed achievable.In fact, the total
number of CFHTLS type Ia SNe observed by 2004 February should already exceed
previous detections.The first papers
are in preparation, and current plans are for an equation of state paper
to be submitted in the spring of 2004.
Wide Survey
Because of the Wide Survey's seeing constraints,
this component of the CFHTLS did not ask for QSO time until early concerns
with the WFC were eliminated.Also,
because this component of the CFHTLS has no time constraints it has been
more difficult to obtain the necessary fraction of time for Wide observations
without affecting the goals of the Deep and Very Wide components.The
observing strategy is still under discussion with the current priority
given to large areal coverage versus multi-colour observations.SAC
expressed a serious concern that such discussions appear to be taking place
only within the SG and have not involved the participating CFHTLS communities
at large.SAC reminds the SG that
improved communication between the CFHTLS SG and the member communities
was an important recommendation (#10) at the previous SAC meeting.
Very Wide Survey
Data have been obtained for the CFHTLS Very Wide
Survey at a smaller rate than nominal.Approximately
200 square degrees will have been observed by the end of 2003.30%
of the observed fields have been analyzed and 50 KBO's have already been
discovered.An up-to-date Very Wide
Survey web site is located at http://cadc.hia.nrc.ca/cfht/cfhtlsvw.
SG Activities
A detailed analysis has been made of the PSF anisotropy
of the MegaCam field of view.SAC
was told that despite concerns with the MegaPrime WFC, 30 to 32 of the
camera's CCD's are within the image quality specifications required for
cosmic shear analysis.
A report of apparent fringing in MegaPrime u' images
prompted a search for a possible red 'leak' in this filter.No
evidence for such a leak has been found.
CFHTLS-related recommendations - See also the Board of Directors'
comments here
There continue to be a few concerns related to the
CFHTLS science programs, the Steering Group (SG), and the Data Oversight
Group (DOG).These have led SAC to
make a number of recommendations.
The SAC is concerned about the image quality provided
by the MegaPrime WFC.If CFHT's study
of L1 of the WFC indicates the presence of a serious problem what is the
impact on LS science goals?
SAC Recommendation #5:
SAC
requests that the CFHTLS Steering Group conducts a thorough investigation
of the impact of the less-than-optimal MegaPrime image quality on CFHTLS
science goals and presents a report to SAC early in 2004.
As mentioned briefly above, the SAC is concerned
that some changes in observing strategies are being decided by survey coordinators
with no discussion outside the SG, and occasionally only with limited discussion
within the SG itself.While SAC believes
communication by the SG with the outside communities is improving, it could
still be better.Since many users
will approach the CFHT home page first for information about the CFHTLS
it is important that this web site provide links to the survey web sites
given above.Some of the current
links on the CFHTLS site have little or no information and should be updated.This
leads to the following recommendation:
SAC Recommendation #6:
SAC
requests that CFHT ensure that all current information related to the CFHTLS
is readily available on the CFHT's CFHTLS web page.SAC
is pleased to see the detailed, frequently updated web sites available
for the various components of the CFHTLS, and links to these sites should
be prominently featured on the CFHTLS entry page.
SAC expects the first public release of CFHTLS images
and data products early in the summer of 2006.A
detailed plan for this data release must be made very soon to ensure that
queue priorities and schedules are well defined for the next several semesters.This
forms the basis of another SAC recommendation:
SAC Recommendation #7:
SAC
requests that the CFHTLS SG present them with a summary of the plan for
the first CFHTLS public data release in the summer of 2006 well in advance
of the 2004 May SAC meeting.Contents
of the data release must be discussed with the participating CFHTLS communities.This
document should include a clear indication that the queue schedule and
priorities can meet the requirements for this data release.
The SAC is very excited to see CFHTLS science ramping
up, especially for the SNe and KBO programs.The
committee expects that wider scientific involvement of the CFHTLS communities
will increase significantly when Elixir-processed CFHTLS images are released
to the CADC and made available for retrieval.TERAPIX
should also make their CFHTLS data products available to the CADC (and
hence the community) as quickly as possible.Unfortunately
no mechanism describing the transfer of data products between TERAPIX and
the CADC has been produced and this will make the distribution of TERAPIX
products difficult.Because of this
SAC makes the following two recommendations:
SAC Recommendation #8:
SAC
urges CFHT to provide the CADC with Elixir-processed CFHTLS images as soon
as possible and that the CADC also make these images available to the communities
as soon as possible.The availability
of these data products should then be widely advertised to the CFHTLS communities.
SAC Recommendation #9:
For
the information of the CFHTLS member agencies, SAC notes that an Interface
Control Document (ICD) for the transfer of data between the CADC and TERAPIX
has not been developed.Until such
a document is produced TERAPIX-processed CFHTLS data products will not
be available for distribution to community astronomers.SAC
recommends that the DOG ensure that such an ICD be developed in a timely
fashion.
SAC
also makes the following recommendation to the CFHTLS SG:
SAC Recommendation #10
SAC requests that the CFHTLS SG produce
a detailed summary of the progress of the CFHTLS components suitable for
review by SAC and the national TAC's.This
progress report should be made publicly available by 15 April 2004 to enable
possible discussion at the 2004 CFHT User's Meeting.A
more formal external review will be conducted in the fall of 2004.
4. WIRCAM
Steering Group
The previous SAC recommendation, based on extensive
SG and SAC discussions, indicates that only 30% of the scheduled WIRCAM
time per semester would initially be available for WIRCAM 'surveys'.After
additional discussion, the SAC and SG do not feel that this represents
a significant enough allocation of time to warrant the considerable effort
required to attempt to define a Legacy style survey.On
the order of 100 WIRCAM nights allocated over a five-year period will simply
not be competitive when compared to other large near-infrared surveys currently
being planned.
The SG and SAC recognize that there is little support
from some member communities for Legacy-style surveys with WIRCAM.However,
based on the SG?s ?call for ideas? for WIRCAM surveys, there is obviously
significant interest in the possible execution of ambitious scientific
programs requiring large amounts of observing time over several years,
likely involving more than one of the member communities.SAC
also recognizes the fact that users of other instrumentation, e.g. Espadons,
may also have similar requirements for significant blocks of observing
time.However, the current mechanism
for assigning significant amounts of time to multi-agency proposals is
seen as very unsatisfactory, and has proven to be unsuccessful in the past.
After a lengthy discussion, the SAC agrees that
a new mechanism needs to be implemented by the member agency Time Assignment
Committees (TACs) and proposes the following as a possible procedure for
the review of large, multi-agency (joint) proposals, requiring time over
several semesters.This should be
reviewed and refined by the national TAC?s, the SAC, and the BoD.
SAC Recommendation #11 - See also the
Board of Directors' comments here
·SAC
defines a ?large joint proposal? as any proposal requesting 30 or more
nights over a two-year period and submitted to two or more member agencies.
·Such
large, joint proposals should be accepted for any CFHT facility instrument.
·The
first Call for Proposals (CfP) for such large programs will be made at
the 2004 CFHT User?s Meeting on 14 May 2004.
·The
large joint proposal deadline will be 1 September 2004.
·Each
submitted large program proposal will be reviewed by a joint TAC consisting
of equal numbers of members from the TAC?s of each participating agency.Members
in the joint TAC will be selected by the national TAC chairs and should
include a sufficient range of scientific expertise to enable a fair review
of all large joint programs.
·The
joint TAC meeting will take place on approximately 15 October 2004, just
in advance of the national TAC meetings to ensure that the large programs
can be reviewed in comparison to normal proposals.
·Accepted
large programs will have nights allocated according to the fractional allocations
proposed by the applicants.
·The
SAC TAC will review time allocations as usual at the 2004 November SAC
meeting.
·Large
programs requiring more than two years of observations must be resubmitted
every two years for review.
·Based
on current telescope time allocations additional CfP?s for large programs
may be made each year.
5. Telescope
Use and Scheduling
C. Veillet presented the preliminary 2004A schedule
to SAC after the SAC TAC members had reviewed it.He
noted that there has been a significant decline in demand for AOB time
from the French over the last several semesters.He
also pointed out that MOS runs can have a large impact on CFHTLS science.For
the 2004A semester only a single, very highly ranked 5-night Canadian MOS
program was scheduled by relaxing the normal ?8-night rule? for instrument
set ups.
At the previous SAC meeting the question arose as
to how the issue of duplicate observations is resolved in the queue.However,
further discussion of 2003B observations with the PI?s indicated that no
urgent action is necessary since there is currently no real duplication
of currently scheduled observations.The
situation, however, will be monitored.
6. 2004
User?s Meeting
Just prior to the SAC meeting a final selection
of the venue for the 2004 CFHT User?s Meeting was made.The
two and one-half day meeting will be held from 13-15 May at Painter?s Lodge,
near Campbell River, British Columbia.A
web page and First Announcement will be released soon.A
brief discussion of the meeting program took place. The first day of the
meeting is expected to be devoted to early CFHTLS science.The
second day will include WIRCAM and Espadons talks and other contributed
science talks.The final morning
will be devoted to discussions of CFHT?s future and a look back at the
25 years of CFHT excellence.
7. CFHT
Future
To provide the SAC with information on which to
base possible future instrumentation recommendations on, C. Veillet gave
a brief summary of the state of CFHT?s past, current, and (anticipated)
future operating budget.He noted
that the current surplus will be exhausted in FY2007/2008 if agency funding
remains at the current level and if all current services are maintained.
At the end of 2005, CFHT instrumentation should
consist of MegaPrime, WIRCam, Espadons, Pueo, MOS, and Gecko.SAC
will almost certainly have to revisit the issue of decommissioning MOS
and Gecko at this time.
He also pointed out that a possible two-stage, or
other form of advanced Pueo Nui might be an appealing option for CFHT to
retain and use existing technical expertise, increase the contributed R&D
efforts of CFHT?s member partners, and perhaps open up a new era of optical,
diffraction-limited imaging with 4-m class telescopes, possibly including
a laser guide-star system.
8. Other
items
· CFH12K
disposition
C. Veillet gave a brief summary of the current status
of the CFH12K camera.An advertisement
of the possible sale or trade of the camera for observing time on other
telescopes was circulated on the CCD Users email distribution list.Four
responses were received from telescope facilities ranging in size from
1.5 to 6.5-m.This led to the following
SAC recommendation:
SAC
Recommendation #12:
SAC
requests that CFHT present a report on options for the possible sale or
exchange of telescope time for the CFH12K camera at the next meeting.
· Staff;
Astronomy Group
C. Veillet provided a summary of the status of the
search for a new Canadian resident astronomer.A
number of good Canadian candidates will be interviewed very soon.Several
additional American candidates may be encouraged to reapply for the UH
resident astronomer position (to replace E. Magnier) once IfA has posted
an advertisement for the position.
· SAC/TAC
membership; chairperson
This meeting represented the last SAC meeting for
French member G. Soucail and Canadian member P. Bastien.P.
Petitjean will assume the role of SAC chairperson on 1 January 2004 and
the BoD will select a new Canadian vice-chairperson.
· Next
meeting
The next SAC meeting will be held on 17-18 May 2004
at the HIA Dominion Astrophysical Observatory in Victoria, BC.