107th Meeting of the Canada-France-Hawaii Telescope

Scientific Advisory Council

29-30 May, 2025, held in hybrid mode at Lac à l’Eau Claire, Québec, Canada


After deliberation during the Board of Director's meeting on 15th July, 2025, the CFHT Board of Directors, in consultation with the Executive Director, endorse the following SAC recommendations:

Recommendation 1 Wenaokeao Commissioning Schedule
Recommendation 2 Recoating of Primary Mirror
Recommendation 3 Investigation of Blue-wavelength Efficiency Loss
Recommendation 4 LP Survey Completeness
Recommendation 5 LP Completeness Projections and Adjustments

Report of the 107th meeting of the CFHT Scientific Advisory Council, May 2025

The 107th Science Advisory Council meeting was held at Lac à l’Eau Claire, Québec, Canada, in hybrid mode on May 29-30, 2025.

SAC members, Alan McConnachie, Ting Li, David Tholen, Ken Chambers, Ryan Cloutier, Stéphane Arnouts (chair), attended the meeting in person, and Philippe Mathias, Scott Chapman (vice-chair), Isabelle Boisse, and Mathias Schultheis attended remotely. The CFHT Executive Director, Jean-Gabriel Cuby, the Director of Engineering, Kevin Ho, the Director of MSE programs, Andy Sheinis, and the Director of Science Operations, Nadine Manset, gave presentations and participated in discussions.

Executive Director J-G Cuby presented the Guiding Principles for the Maunakea Observatories and the activities undertaken with the local community. Once again, SAC endorses the importance of these activities and commends the executive director for his leading role in developing the set of Guiding Principles for the Maunakea Observatories.

SAC heard about the recent and upcoming departures of several key persons. SAC would like to acknowledge Mary Beth Laychak on her departure and wants to congratulate her for her leadership in local community engagement and her pivotal role in the Maunakea Scholars program. SAC offers its best wishes for her future endeavors. SAC has also been informed of the planned departures of Andy Sheinis and Sam Barden in mid-2025. SAC offers them its warmest wishes for a fulfilling retirement and expresses its deep gratitude for their outstanding efforts and contributions to the MSE project and CFHT over the years.

SAC commends CFHT for addressing long-deferred maintenance and for ensuring the knowledge transfer and documentation, especially important in light of upcoming retirements.

The workload on the operations staff is expected to increase following the departure of one of the French resident astronomers, as no candidate applied for the open position. This leaves CFHT with only five resident astronomers — down from seven in the 2005–2013 period. Continued automation of the observing queues should help mitigate the impact. SAC emphasizes that all partner agencies must fulfill their commitments. In light of the staffing challenges, SAC encourages the Board to explore alternative solutions to ensure the continued smooth functioning of night operations.

SAC was informed that the delivery of Wenaokeao to CFHT is expected in May/June 2026. SAC supports the Director’s recommended aggressive timeline to complete commissioning within three months of delivery. SAC also endorses prioritizing Wenaokeao’s operation and testing—specifically for Modes 1 through 3—at least one semester before the start of the Community Survey. Given the Community Survey’s strong reliance on Mode 3, ensuring its readiness is critical to mitigating any significant risk.

SAC would like to thank the community for the excellent input on the Community Survey during the Users’ Meeting. While all the details are given at the end of this report, the main points are summarized here. The Community Survey period will run from 2027B to 2032B with two major survey programs, one using Wenaokeao and one using MegaCam, each over 400–700 nights.

A Community Survey Working Group (CSWG) will be formed to oversee planning and implementation, set the proposal scope, review criteria, and manage the call process. The proposals should show efforts to engage a broad community and will be externally peer-reviewed. Key milestones include a call release in September 2025, external reviews and reconciliation process through 2026, and a survey start in semester 2027B.

In this period of uncertainty regarding CFHT’s future, it is essential that the SAC and the Board align on a shared long-term vision to best position the Observatory within the evolving astronomical landscape. SAC regrets the Board’s decision to pause work on MSE, especially the feasibility studies assessing the potential for repurposing the CFHT site for a larger telescope. Realizing a compelling long-term vision for CFHT will require establishing new collaborations and securing credible budgets with major partners who share a strong interest in its core scientific capabilities. Achieving this will demand effective communication, collaboration, and transparency among the SAC, the Board, and the Observatory.

Users' Meeting

The 14th CFHT Users’ Meeting was held from 26 to 28 May 2025 at Lac-à-l’Eau-Claire, Québec, Canada, immediately prior to the SAC meeting. Of the 154 people who registered, 82 attended in person and 69 joined remotely, reflecting both the vitality of the community and the utility of hybrid participation.

The scientific program was exceptionally rich. From 84 submitted abstracts, the SOC assembled 39 talks across five science sessions plus one devoted to Large Programs -- each showcasing CFHT data, alongside seven presentations in the “Future Opportunities with CFHT” session, 13 oral contributions proposing concepts for the upcoming Community Survey, and a poster track of 18 on-site posters (each introduced by a one-minute flash talk) and 10 remote posters. Three sessions were dedicated to shaping the forthcoming community survey(s), featuring science cases that underscored the unique capabilities of instruments such as SPIRou + ESPaDOnS (Wenaokeao) and MegaCam. It was also satisfying to see the interest in CFHT from new communities that have not been historically involved in the Observatory. Further sessions explored Community Astronomy initiatives and provided updates from the MaunaKea Observatories. Throughout, open discussion offered the SAC valuable guidance on how best to prepare and organize the community survey.

SAC was impressed by the high level of participation, the breadth and depth of the scientific results, and the strong presence of early-career researchers. Their contributions, spread across multiple dedicated sessions, testify to CFHT’s continued scientific relevance and its success in nurturing the next generation of astronomers.

The committee gratefully acknowledges the impeccable organization of the Local Organizing Committee and CFHT staff -- especially Nadine Manset -- whose efforts created a memorable and productive meeting. SAC also thanks Benjamin Kucher of the Canadian Archaeological Association for sharing insights into Indigenous Archaeology that enriched the astronomical community’s perspective.

Wenaokeao Update

Wenaokeao is an optomechanical device developed by IRAP and installed at the Cassegrain focus of CFHT. Based on the VISION device at TBL, its primary function is to split light between ESPaDOnS and SPIRou, while preserving the polarization state of the light.

Wenaokeao was delayed due to internal prioritization conflicts at IRAP. However, after intervention from CNRS-INSU and the CFHT Board, the project was restructured with dedicated project managers at IRAP/OMP and CFHT. A Design Review in April 2025 confirmed that the instrument design meets scientific and technical requirements. Key recommendations included improving the delivery schedule, ordering long-lead optical components promptly, assigning a project scientist (Luc Arnold), and preparing detailed risk mitigation and commissioning plans. An optical engineer will be hired to support integration and testing activities in Toulouse in September.

Delivery at CFHT is expected for May/June 2026. SAC endorses the CFHT timeline for the commissioning and endorses Wenaokeao as the priority for when it arrives. CFHT expects to install and commission it in three months.

The CFHT S/W team updated the requirements for the “Observations Execution System” that are nearing finalization (see also Kealahou update). The availability of Mode 3 is a priority for the Community Survey. However, its implementation might require shifting to 2027B if 2027A needs to be allocated for testing and operational performance of Mode 3.

A Design Review was conducted on April 29th to verify that the design meets scientific objectives and system requirements, with acceptable risks and within cost and schedule constraints (a documentation report will be available soon). However, two risks have been identified:

  • Cost: Shipping tariffs may exceed previous estimates. Given the current international situation, CFHT and IRAP should closely monitor tariff developments for instrument transportation.
  • Cross-talk: Based on VISION measurements, the U→V cross-talk remains within specifications (<2%) for Modes 1 and 2. However, Mode 3 exhibits a measured cross-talk of 4%. This elevated value may originate from the dichroic positioning. Notably, Wenaokeao employs a different dichroic mount configuration. It should be emphasized that while 4% represents an increase, this level remains acceptable for magnetic field measurements and should only impact very weak field observations.

RECOMMENDATION #1: SAC agrees with CFHT that the schedule for commissioning Wenaokeao must be aggressive and that Modes 1 - 3 should be ready for deployment before the end of 2026B. SAC recommends that a realistic schedule for all post-shipping work be developed in the near term, and that upon delivery of Wenaokeao, it becomes the top priority for CFHT staff. This must include ensuring that the observatory software can accommodate efficient Mode 3 observations.

Back to top

Kealahou Update

The Kealahou development team reported a productive first half of 2025 that included:

  • Completing the redevelopment of the MegaCam SNR Modes. This included
    • The introduction of two SNR modes: Standard (per exposure mode) and Cumulative (based on the total SNR over multiple exposures).
    • The introduction of the "auto-snap" exposures to automatically determine the sky level to seed the ETC.
    • Several minor improvements either completed or finalized. The full feature set is expected to be available for all MegaCam programs starting in 2025B.
  • The implementation of K2 user collaboration tools. These features will allow PIs to set the access permissions for individual collaborators within their programs. The tools have the capacity to treat collaborators who were named during the K1 phase as well as new collaborators. The user collaboration tools are expected to be available for the K2 submission phase in ~June 2025.
  • The GitLab migration was successfully completed in November 2024, with all source code now managed in-house.
  • The Production database upgrade had to be postponed following the discovery that the Kealahou database software and CFHT’s current Java version (Java 8) are incompatible. The Java upgrade is now a prerequisite for the database upgrade to be completed. The timeline is unspecified.

Upcoming projects include developing Rapid ToO capabilities & integration with the Astronomical Event Observatory Network (AEON). Progress on these efforts has been delayed by NSF grant disbursement. However, the Kealahou team has continued with initial efforts focused on stabilizing the Kealahou API and addressing known bugs. Progress is expected to be accelerated over the summer months. The Kealahou team will also prioritize Wenaokeao Instrument Integration. While the timeline for Wenaokeao delivery and commission has shifted, the team has finalized its user and internal software requirements. A global software plan for Wenaokeao integration is under development.

The Kealahou team also highlighted its progress on bulk data handling improvements in K2 (AstroRes target list uploads, entity duplication), user account deletion features to be compliant with GDPR requirements, new internal software development guidelines, and continued emphasis on bug fixes and system support. The team remains committed to executing the 2025 development plan.

The SAC commends the Kealahou team on their efforts to improve and expand on the very successful Kealahou platform. The SAC wishes to highlight the smooth transition from PH2 to Kealahou for MegaCam and on the Kealahou team’s rapid responsiveness to inquiries from its user base. The SAC extends its gratitude on behalf of the CFHT user community and encourages the Kealahou team to continue their efforts.

MSE

After the December 2024 SAC meeting, the Board issued a statement that it is pausing the MSE project. In response, the Observatory undertook an effort to ensure all material and documentation relating to MSE was completed, collated, and stored in a manner that will ensure its easy access in the future. This effort is nearly complete, and includes pre- and post Conceptual Design Review material, design archives (Quad-Mirror, Pathfinder/IFU), and supplementary content like meeting notes and newsletters, all indexed in the Project Document Index (PDI). The final phase involves moving in-progress design files from SharePoint and engineers’ directories to the PDI. Completion is expected by late May or early June 2025.

SAC thanks all previous members of the MSE Project Office and CFHT staff that have contributed to the MSE effort over the last decade or more and commends CFHT for this final push to ensure the documentation and design information remains accessible. This will be especially important for when work on MSE is re-initiated. CFHT staff should be very proud of the transformative impact that their efforts on MSE have had on the international discussion of wide-field spectroscopic facilities.

In addition to the pausing of MSE, SAC was provided with an update on the progress by Sam Barden on the pupil-splitting concepts for which he received NSF funds. SAC was delighted to see the advanced stage of these studies and encourages these results to be published as soon as possible.

CFHT Operations

MegaCam u-band zero point

The SAC is gravely concerned about the rapid decline in u-band throughput, which has dropped by roughly 0.35 mag every three years since 2011 — a trend not seen before that date. MegaCam’s blue sensitivity is pivotal for the forthcoming community survey where the blue sensitivity of MegaCam is a major interest. The zero-point loss will significantly increase the duration of the survey.

Sulfur dioxide from the volcano can have a very significant impact on the mirror coating. Both Subaru and Pan-STARRS have implemented new humidity limits, i.e., if more than 1 ppm sulfur dioxide is present in the atmosphere, to set the maximum humidity limit for dome closure to be at 50%. CFHT might consider adopting a similar protocol. Ideally, SO2 detectors would monitor the SO2 level (inside and outside the dome); in the meantime, the SO2 forecast can be used: http://weather.hawaii.edu.

RECOMMENDATION #2: The SAC notes a zero-point decline of roughly 0.4 mag (about a 30-35% drop in throughput) and recommends recoating the primary mirror at the earliest practical opportunity -- ideally in early 25B -- while keeping observing downtime at a minimum.

Back to top

RECOMMENDATION #3: The SAC recommends that the CFHT team continue to investigate the underlying cause of the blue-wavelength efficiency loss and that CFHT calculate the optimal recoating interval, using empirical trends, to balance coating longevity against observing efficiency.

Back to top

SPIRou

Minor operational issues were resolved satisfactorily.


ESPaDOnS

Minor operational issues were resolved satisfactorily. We support the plan to automate the pumping of the detector while warm so that this can be done without manual intervention at the summit.

WIRCam

We support keeping WIRCam cold until a decommissioning forecast suggests otherwise.

SITELLE

There were no operational issues.

Nānā`ao (former ASIVA, Maunakea Observatories)

Congratulations on restoring this important capability.

MKAM

Congratulations on restoring this important resource to operational status.

Bridge crane VFD/ EStop upgrade

We look forward to the planned campaign in July to complete the Bridge crane upgrade. Adding true Estop is an important safety consideration.

Freight elevator

We look forward to the restoration of the freight elevator to full operational capability.

Dome Louvers and Vents

Congratulations on the repair of the dome louvers. We look forward to the repair of the L5 vane and the plan to address the actuators for all the vanes. This will help dome seeing.

Cyber security

We look forward to the implementation of a DMZ and 2-factor authentication as mitigation for the very real threats to cybersecurity. We also look forward to the computer room enclosure upgrade.

Deferred Maintenance Report

Critical spares: The sitution is in good shape

Documentation: This is a high priority as several key staff members will retire or exit soon.

Building glycol chiller upgrade: We look forward to the chiller upgrade and note the recommendation to switch to food-grade glycol for environmental risk mitigation with the new chiller.

Air-compressor: We look forward to the completion of the air compressor replacement.

Telescope hydraulics: We look forward to the telescope hydrolics hose replacement and hope this solves the problem.

Dome shutter: We support the proposed gearbox upgrade.

Dome system maintenance: We encourage progress on the dome system maintenance program.

Summit UPS upgrade: We support the feasibility study to stabilize the UPS system.

TCS IOC upgrade: We support the feasibility study into moving away from the VME hardware and VxWorks OS.

Risk Register

The SAC thanks the CFHT staff for making the Risk Register available to them. This is an outstanding tool for tracking the important risks to look for. We note that every issue that led to a significant loss of observing time was anticipated by the Risk Register, emphasizing its critical importance and the need to proactively address the high-risk items.

Science Operations

QSO Report Semester 24B

For the 2024B semester, SPIRou was scheduled for 72 nights, MegaCam for 49 nights, SITELLE for 27 nights, WIRCam for 23 nights, and ESPaDOnS for 13 nights. Completion percentages for A and B programs were 108, 90, 81, 86, and 76 for those same instruments, respectively. C-ranked programs that received observing time received the equivalent of 2 percent of the time observed for A- and B-ranked programs. Eighteen proposals for Director’s Discretionary Time (DDT) were approved, totaling 7.24 nights. Overall, 17 percent of the nights were lost due to bad weather, with SITELLE suffering the most at 27 percent, and MegaCam suffering the least at 10 percent. Compared to the 2019-2023 five-year period, 2024B had the smallest weather losses. 2.7 percent of the time was lost to technical issues, and 8.5 hours were used for engineering. The agency balance for all instruments was 100 percent completion for NRC programs, 97 percent for CNRS+Opticon programs, 87 percent for UH programs, 94 percent for NAOC, and only 62 percent for ASIAA.

The good weather in 2024B continued into the beginning of 2025A, allowing great progress to be made on UNIONS and CLASSY, which had received extensions beyond 2024A to recover from losses caused by the crane failure.

Phase 2 Semester 25B

For the 2025B semesters, 80 proposals have been submitted in total leading to a pressure for NRC of 1.52, CNRS 3.13, UH 0.67, ASIAA 1.15, and NAOC 0.58. The LPs UNIONS and PRISTINE have been allocated 10 nights each, and PLANETS for 60 nights. For 2025B, the highest demand comes from SPIRou, following the instruments of MegaCam, ESPaDOnS and SITELLE while the demand for WIRCam remains low.

Large Programs

Ending LPs

In their report, the three science teams warmly thanked the QSO team, in particular, for the exchanges and the help with the scheduling, and also thanked the CFHT staff for their support throughout.

SPICE

SPICE LP ended in 2024A, and its science was extended through PI program time allocation. It began in 2022B after the end of the SLS, lasting then five semesters. The program gained on the crane failure in 2023-2024 that often led to longer SPIRou runs. SPICE was then allocated 1220h (174.3 nights) + 223h (31.9 nights). The final status ended with 246 nights of validated data with almost 120% of the full allocation. The team re-emphasizes the need to follow the observing strategy with a dense measurements of the stars to meet the science objectives.

As the SLS survey, the program was split into three WP: blind search of planetary systems, follow-up of transiting planets, and magnetized star-disc and star-planet interactions. Compared to the SLS, SPICE focused on very low mass stars or star-disc with high accretions rates that were not in the science core of the SLS. Each WP has around a third of the time allocation (with a little more for the WP1).

For a Large Program within a broad consortium, it's a bit concerning that out of the 20 listed papers related to SPICE, 8 were written by just three individuals, even if the list is noted as non-exhaustive. We encourage the teams to move forward with publishing the remaining ~20 expected papers, and to ensure the broader community has access to the high-quality, science-ready data.

UNIONS

The CFIS-UNIONS program gained in 24B/25A due to excellent observing conditions and the prioritization of the program to the other LP MegaCam. The initial coverage plan in the r-band is now 100% completed and the u-band is now at 85% (some of the 25B-26A allocation will be used to go near 100%).

The allocation of the 24B-25A semesters of 148h has a completion rate of 70% and the program will begin to extend to the declinations down to +15° (compared to +30° for now) as soon as all the original survey is done.

As of early 2025, 14 papers have been published or submitted, bringing the total to 45 since the start of the project. A highlight is the publication of the first photometric redshift measurements based solely on UNIONS data (Gwyn et al. 2025). At the same time, overlapping measurements with the Q1 Euclid data release have resulted in major collaborative science efforts, with 19 papers already published by early 2025. Meetings between the UNIONS and Euclid teams are ongoing to support and strengthen this successful collaboration.

CLASSY

CLASSY was granted an extra semester in 2024A/2025B allocation to recover from losses due to the crane failure and is now close to completion. A total of 56 nights was allocated plus 90h of extension plus some director’s time (48h), with a mean validated allocation of around 84%. The program was cut into six blocks, each block being multiple long stare observations of a field of view. One programmed block cannot be observed due to bad weather and the observational window being in competition with UNIONS. An additional science case was derived from the observations as lightcurve characterization or measure orbits of 128 new Saturn moons.

The team noted again an issue with Phase 2 systems interaction with ephemeris pointings. The CLASSY team have worked extensively on it with the QSO team but the problem continues. The CLASSY team has found a way to circumvent it (however, it is time-consuming).

The program aimed to secure the detection of TNOs and recover their orbits. The team has just finished analyzing the first-year fields. They have excellent detection rates with around 150 objects per pointing and limiting magnitudes between 26.1 and 27 in r-band. The program was highlighted in different seminars and conferences this year, but the SAC looks forward to seeing publications out of this program.

New LP

PLANETS

The PLANETS program began its observation in 2025A with 60 nights allocated, of which 24.8 nights were observed at the time of the report. It can be noted that compared to the previous SPIRou LP, PLANETS includes a fourth WP dedicated to the observation of planetary atmospheres.

The SAC notes that several LPs need more than 80% completeness to meet their primary science objectives. For instance, UNIONS -- an essential ground component of the Euclid mission -- cannot deliver its core science at the 80% completeness level because all LPs must conclude by semester 2027A. With the Community Survey (CS) beginning in 2027B, the SAC issues two recommendations. The first is directed to current and future LP PIs (excluding CLASSY and UNIONS, which will already finish in 2025A); the second is directed to the CFHT. Together, these recommendations aim to ensure that every LP reaches the level of completeness required for its main/primary science goals by the end of 2027A.

RECOMMENDATION #4: Beginning with the next bi-annual report, PIs of each LP must include a section on lessons learned that could benefit future LPs or Community Surveys. Furthermore, they must quantitatively report survey completeness, stating the current completeness, the minimum completeness required to achieve the LP’s primary science goal, as well as a justification.

Back to top

This information from the bi-annual report will allow the SAC, at its next meeting, to advise the Board on LP priorities (vs. individual PI proposals) and to confirm that each program is on track to finish the observations needed to achieve its primary science goal by 2027A. The SAC affirms that the completeness target for each LP -- whether 80%, 90%, or 100% -- must be set by the scientific requirements of the program, not by a generic threshold. The CFHT QSO team should therefore adjust LP and PI times so that the three ongoing/future LPs (UNIONS+, Pristine, PLANETS) can, if feasible, reach the completeness required by each LP to achieve their main/primary science goal by 2027A.

RECOMMENDATION #5: For the next SAC meeting, the SAC requests CFHT to provide a semester-by-semester projection of expected completeness for 25B, 26A, and 26B for each of the three new LPs. This will allow the SAC to compare those projections with the PI reports described in Rec. #4. The SAC will then recommend adjustments to the scheduling priorities on an “as needed” basis, to ensure that all three LPs attain their primary science goals by the end of 27A.

Back to top

Post 2027 Community Surveys

The SAC was delighted to see the high level of interest and engagement in the Community Survey sessions at the recent Users’ Meeting and was pleased by the range of interesting and large observing programs that were suggested. SAC would like to thank the community for excellent input and suggestions during the Users’ Meeting as to how best to proceed to the next stage.

Boundary Conditions on the Community Survey

The SAC recommends that the Community Survey development takes place with the following high-level requirements:

  • The entire Community Survey period at CFHT should be from 2027B-2032B.
  • As much as 85% of the available observing time from Canada and France should be allocated to the Community Survey, with a mechanism for participation by the UH community on a survey-by-survey basis to be formalized at the Board level.
  • Science teams can include members from the international (non-CFHT) community.
  • Ensuring the Community Surveys reach their primary science goals will be a higher priority at CFHT than PI programs running at the same time from the agencies participating.
  • All members of the science teams and members of those communities that are contributing time should be able to have early access to the raw, processed, and high-level data products from the surveys.
  • There must be a commitment by the survey teams to provide data access to the community, including regular (~1-2 times per year) releases of high-level data products to those communities.
  • Community Survey proposals should be externally peer reviewed by a panel of experts:
    • For cases of multiple work packages within a single proposal, the panel should provide clear input on the relative priorities of various survey components
  • The community should expect only two programs to be accepted as a result of the main call for proposals. These programs will include:
    • A program using ESPaDOnS/SPIROU (Wenaokeao) for 400 - 700 nights (7 hrs/night) of time that uses predominantly bright/grey time in ~2 week blocks per month that spans RAs and observing conditions.
    • A program using MegaCam for 400 - 700 nights of time (5hrs/night) that uses predominantly dark/grey time in ~2 week blocks per month that spans RAs and observing conditions.
  • There should be evidence at proposal submission of the survey team trying to incorporate as large a community as possible, and this should be a factor in the assessment of the programs by the review panel.
  • Proposal teams should expect that all successful long-term observing programs will undergo external mid-term reviews of their scientific output and progress to date.

Establishing the Community Survey Working Group

In order to facilitate future planning for the Community Survey, the SAC has established a Community Survey Working Group (CSWG) that will be responsible for guiding the future development of the Community Survey initiative. The composition of this group includes:

  • two members of SAC with expertise in Wenaokeao science (C+F)
  • two members of SAC with expertise in MegaCam science (C+F)
  • one member of SAC from UH
  • one member from CFHT with knowledge of observing practicalities at CFHT
  • two members from the community with expertise in Wenaokeao science (C+F)
  • two members from the community with expertise in MegaCam science (C+F)

For the SAC, the following people have been identified as inaugural members of this group:

  • SAC: Isabelle Boisse (F, Wenaokeao)
  • SAC: Ryan Cloutier (C, Wenaokeao)
  • SAC: Ting Li (C, MegaCam)
  • SAC: Mathias Schultheis (F, MegaCam)
  • Ken Chambers (UH)

SAC would like to propose Nadine Manset (with her agreement) as the CFHT representative.

The immediate task for this working group is to identify the community members.

We recognize that the working group will need to manage perceived conflicts of interest, and we suggest that membership of this group should not include anyone likely to be a PI of a Community Proposal, but that it is unrealistic to require that members (including SAC members) may not be Co-Is of submitted proposals.

Charge to the Community Survey Working Group:

The Charge to the CSWG is as follows:

  • Establish the scope-of-call of the Community Survey, in line with the above high-level guidance from SAC.
  • Establish the process, criteria, and timeline for evaluation of Community Survey proposals, in line with major milestones established by SAC and CFHT.
  • Establish a review process for Community Survey proposals, in line with major milestones established by SAC in consultation with CFHT.
  • Initiate and manage the call for Community Survey proposals, and proactively engage and work with all interested parties to ensure the best possible alignment of submitted proposals with expectations of the WG. This includes ensuring teams engage with a wide science community in defining the overall scope of their proposals.
  • Manage any perceived conflicts or complaints between teams or individuals.
  • Post-review, reconcile any conflicts between the outcome of the process and observatory/community constraints to ensure efficient and scientifically productive use of CFHT observing time.
  • The WG should expect to provide a written report and a presentation/discussion to the SAC at each of its upcoming meetings during this time-period.
  • The WG, with the proposal teams, should work with the CFHT team to propose a plan to engage the local community in the Community Survey as a recognition of the importance of fostering a community-based model for astronomy in the long-term future.

High-level Milestones for the Community Survey Working Group to Consider:

The following high-level milestones have been identified by the SAC, and the WG should plan its activities based on these milestones:

June 2025 Formation of the Working Group
September 2025: Release of the Call for Community Surveys
March 2026 Call deadline
March - August 2026 External Peer Review process
Sep 2026 - March 2027 Reconciliation phase led by WG in collaboration with survey teams(s) to rationalize the outcome of the process with observatory/community constraints to ensure efficient and scientifically productive use of CFHT observing time
April 2027 Board final approval of the Community Survey
May 2027: Phase (K2) opens for semester 2027B for PI programs and the Community Survey
Start of 2027B: Start of the Community Survey

Operational and Development Priorities

  • Normal Operations
  • Risk mitigation and deferred maintenance
  • Documentation and succession planning
  • Kealahou (including Wenaokeao Mode 3)

Next SAC Meeting

The next SAC meeting will be held in person in Waimea, Hawaii, on Monday, December 1 to Wednesday December 3, 2025.